Steeles Avenue East road closure ahead as crews prepare south side of new underpass to welcome traffic

Short-term traffic detours for vehicle and pedestrians are coming to Steeles Avenue East. But when the project is complete, it will eliminate the need to wait for trains to pass – improving traffic flow, safety and access to GO train service via new pedestrian bridges. Steeles Avenue East is getting an upgrade by moving below grade. To safely divert traffic to the south side of … Continue reading Steeles Avenue East road closure ahead as crews prepare south side of new underpass to welcome traffic

Rarely used “top-down” construction technique used to build new rail bridge at Milliken GO

A new rail bridge is taking shape at Steeles Avenue East near Milliken GO Station. Since June, the construction team has been focused on advancing this work and recently completed a concrete pour of the bridge deck. This pour was a significant milestone as it connects the substructure elements (abutments and pier) with the superstructure (deck), completing a critical phase of construction. With the entire … Continue reading Rarely used “top-down” construction technique used to build new rail bridge at Milliken GO

Rendering of rail over road grade separation at Steeles Avenue East near Milliken GO Station

Stouffville GO – Dropping the road while keeping the flow

Local traffic and pedestrians will keep moving while a new underpass is built on Steeles Avenue East. As a reliable junction, it was getting a failing grade. For the Stouffville rail line, the existing crossing on Steeles Avenue East, near the Milliken GO Station was slowing down vehicles, transit, pedestrians and cyclists. With daily issues of congestion and users experiencing frustration travelling along this busy … Continue reading Stouffville GO – Dropping the road while keeping the flow